Mitsubishi Power puts $490 million into its Savannah turbine plant as backlog hits 35 GW.

Mitsubishi Power will put $490 million into its Savannah Machinery Works in Pooler, Georgia, adding 450,000 square feet and more than 220 jobs. MHI's large-frame turbine backlog is 35 GW, up from 23 GW a year earlier, with recent orders set for delivery between 2028 and 2030. The turbine queue is a real limit on new power, and this is how long the fix takes.

More from The Feed

NEWS

Eco DC says it lined up 30 Dongfang gas turbines for Canadian data centers with no sites named.

Eco DC Solutions says it will be Dongfang Turbine's North American importer for 30 G50 gas turbines, over 2.1 GW in combined cycle, for Canadian data centers. Data Phoenix notes the release names no sites, delivery dates, price or financing. With Western turbines booked for years, buyers are turning to Chinese machines, and that raises its own questions.

Skeptical read: Data Phoenix