IREN's Texas sites add up to 2,750 MW, with Sweetwater 1's 1.4 GW substation already energized.
A breakdown of IREN's own site list puts 2,750 MW in Texas: Childress at 750 MW for Microsoft delivery and Sweetwater at 2,000 MW, with the 1.4 GW Sweetwater 1 substation already energized. The post framed it against the midterm selloff in Texas data-center stocks. The figures come from a company site list read by an investor account, so check them against IREN filings.