Goldman counts 86 data center projects canceled or significantly delayed since January, 76 of them over local opposition

The report, shared with Axios, also puts the median time from a grid connection application to commercial operation at roughly five years. The bottleneck for the buildout is permits, neighbors and power, not chips.

Axios · Madison Mills · Oct 20, 2026

More from The Feed

NEWS

Microsoft walked away from a 50 MW UK data center because grid power will not arrive until the 2030s.

Microsoft dropped its anchor deal for Nscale's planned 50 MW site in Loughton, Essex, after warnings the grid might not deliver power until the early to mid 2030s. The plan was 23,040 Nvidia GB300 GPUs. The customer, chips and money were in place, and the interconnection date still decided it.