NEWS

Alliant Energy raises capex 19% to $15.9B on 3.4 GW of contracted data center load.

Alliant Energy says it has 3.4 GW of contracted data center demand in Iowa and Wisconsin. Its $15.9B plan for 2027 to 2030 adds 1.2 GW of gas generation and 200 MW of storage. A Midwest utility's concrete build list for data center load.

More from The Feed

NEWS

Heavy-frame gas turbines now take about 278 weeks to arrive and transformers about 162, Wood Mackenzie finds.

Wood Mackenzie's Oct 30 note puts heavy-frame gas turbine waits at about 278 weeks and large transformers at about 162. AEP has a plan for SB Energy's proposed 10.4 GW Piketon, Ohio campus, and PJM has refiled a reliability backstop purchase of about 6,800 MW at FERC, with comments due Nov 30. Lead times and the grid moves behind them, in one place.