Alberta data centers have asked for 26,849 MW of power, against a 1,200 MW limit that is already used up.

Requests to connect data centres in Alberta grew from about 19,565 MW in July to 26,849 MW in October, roughly twice the province's record peak. All 1,200 MW of interim room went to two projects, and Phase 2 rules favor projects that bring their own generation. Requests are not approvals.

More from The Feed

NEWS

How an AI agent that reads PLC code and schematics lets maintenance techs troubleshoot like engineers, on The Manufacturing Executive.

On The Manufacturing Executive, former Tesla controls engineer Reece Mullins describes an agent that reads PLC code, schematics and live data so maintenance techs can troubleshoot faster. The goal is to keep undocumented fixes from walking out the door. Mullins founded Metis, so this is a vendor conversation.